Work in Progress:
- Fire alarm raceways are approximately 75% complete.
 - Electric Panel 1J is complete.
 - HVAC duct installation continues on floor 2 and 3.
 - Temporary heaters have been removed from the building.
 - HVAC curb delivered and set on 4/27.
 - Door frame installation and drywall finishing happening throughout the building.
 
Looking forward:
- AHU Air House delivery scheduled for delivery on week of 5/16.
 - New masonry opening to be cut-in on first floor.
 - Fire alarm wire will be pulled to device locations.
 - Remaining demolition and floor tile abatement will take place the week of 5/2.
 - Complete plumbing in restrooms.
 - Drywall taping and finishing throughout.